Electric control cabinet ready for POWER
Since last friday we’re ready to put our main control cabinet into operation. The main components are wired and ready to check them. The check will be likely on next Monday, after that we’re able to continue with the development of the software for the ILC 350 PN from Phoenix Contact.
The circuit diagram has been completely redrawn in E-Plan P8, because the one we used as a blueprint was done in Caddy++, which is not an industrial standard.
Our next steps will be to install a network cable between the ILC 350 PN and the connector on the left side of the control cabinet, furthermore we have to install new banana jacks to preserve the demanded degree of protection. As soon as the shipment with the missing motor contactor is comming, the control cabinet is completed.
Here are some pics of our desktop…
doing the “paper work”, …
and some soldering.

RSS
Filed under:
Thomas Fuchs @ 18th September 2007, 13:56
[…] fleißiger Arbeit ist nun ein deutlicher Fortschritt auf der Projekthomepage zu erkennen. Der Schaltschrank ist bereit für eine Funktionsprüfung, für die M&Ms gibt es bereits ein […]